Why do you add work rates instead of averaging days?
A time says how long the whole job takes, not how much gets done each hour. What piles up when two people work together is output: 30 bags an hour plus 10. So turn times into rates, add, then convert back.
- •(8 + 24) ÷ 2 = 16 hours
- •Slower than Zoya alone
- •30 + 10 = 40 bags an hour
- •240 ÷ 40 = 6 hours
| Test | Averaging the times | Adding the rates |
|---|---|---|
| Answer for 8 h and 24 h | 16 hours | 6 hours |
| Passes the sanity check? | No | Yes: under 8 |
What is the LCM method in time and work?
Fractions like 1/8 + 1/24 are miserable under pressure. The LCM method pretends the job has a size every worker's time divides into exactly: the LCM of their times. Then every rate is a whole number.
Try it on three people. Meher, Rohan and Kabir are editing the fest aftermovie; alone they would need 12, 20 and 30 hours.
- 1
Size the jobLCM(12, 20, 30) = 60 units.
- 2
Rate each worker60 ÷ 12 = 5, 60 ÷ 20 = 3, 60 ÷ 30 = 2 units an hour.
- 3
Combine5 + 3 + 2 = 10 units an hour. Anyone undoing work is subtracted.
- 4
Convert back60 ÷ 10 = 6 hours.
Meher carries half the job. Rates stack like these bars; times never do.
How do you solve time and work questions step by step?
- 1Total work = LCM(9, 18) = 18 units.
- 2Tara does 2 units an hour, Rohan 1.
- 3Together: 3 an hour, so 18 ÷ 3 = 6 hours. Inside the 4.5–9 band. ✓
- 1Total = LCM(16, 24) = 48 units. Kabir does 3 an hour, Aarav 2.
- 2First 6 hours together: 6 × 5 = 30 units.
- 3Left: 18 units for Kabir alone: 18 ÷ 3 = 6 hours.
Efficiency questions flip the method. "Zoya is 50% more efficient than Meher" means their rates are 3 : 2, so use those as units per day. If together they finish in 12 days, the job is 5 × 12 = 60 units, and Meher alone needs 60 ÷ 2 = 30 days.
How do man-days and M1 × D1 = M2 × D2 work?
When every worker is equally good, a job has a size in person-days: people × days. A campus clean-up that 6 volunteers finish in 20 days is a 120 person-day job, whoever does it. More people, fewer days, same product: inverse proportion.
| Volunteers | Days | Person-days |
|---|---|---|
| 4 | 30 | 120 |
| 6 | 20 | 120 |
| 10 | 12 | 120 |
| 12 | 10 | 120 |
Add hours a day and amount of work: M1 × D1 × H1 ÷ W1 = M2 × D2 × H2 ÷ W2. People, days and hours share the load; more work needs more of them.
- 1Effort per board: 12 × 5 × 4 ÷ 60 = 4 volunteer-hours.
- 296 boards need 384 volunteer-hours.
- 3The new team supplies 8 × 6 = 48 a day: 384 ÷ 48 = 8 days.
What are the fastest time and work shortcuts?
- ✓Two workers: a × b ÷ (a + b). Three or more: LCM units.
- ✓Efficiency is the inverse of time. Times 2 : 3 means efficiencies 3 : 2.
- ✓Together in T, one alone in a: the other = a × T ÷ (a − T). Story check: 8 × 6 ÷ 2 = 24. ✓
- ✓Pair sums: add the A + B, B + C and C + A rates and halve.
- ✓Join or leave: count units per phase.
And because CLAT loves money: pay follows work, not hours on the clock. If Zoya and Aarav share ₹1,200 for the bags, split it by what each packed in those 6 hours.
Both worked all 6 hours, so the split is their rates, 30 : 10.
How does time and work hide in a CLAT caselet?
Since 2020, CLAT wraps arithmetic in a paragraph: machines, shifts, breakdowns. A print shop takes an order for 3,600 fest flyers. Machine P alone would print them in 6 hours, Q in 9 and R in 18. No LCM needed: the passage gives the job's real size, so rates come out in flyers per hour.
Turn every "takes x hours" into "does y per hour" before you read a single question.
Which time and work traps cost the most marks?
Most wrong answers here are reading errors, and the options are built to catch them.
| The passage says | What it means | The trap option |
|---|---|---|
| "A leaves after 4 days" | Both work 4 days, then B alone | Treating it as 4 days before the end |
| "A leaves 4 days before completion" | A works T − 4 days; solve for T | Assuming A worked 4 days |
| "How many more days?" | Only the last phase | The total time |
| "Paid ₹X for the job" | Split by rate × days worked | Equal split, or by speed alone |
How CLAT asked it
Twelve men and 5 women can complete a work in 2 days whereas 4 men and 3 women can complete the same work in 5 days. In how many days can 8 men complete the work?
Reveal answer + reasoning
Job = 24 + 10 × 0.8 = 32 man-days (Team 2: 20 + 15 × 0.8 = 32 ✓). Eight men need 32 ÷ 8 = 4 days.
Eliminate first: Team 2 is 4 + 2.4 = 6.4 men strong and needs 5 days. Eight men are stronger, so the answer is under 5: C and D die at once. About 60 seconds.
- A — Counts only the men's 24 man-days in Team 1 and drops the women's 8: 24 ÷ 8 = 3.
- C — Copies Team 2's 5 days, though 8 men out-work 6.4 men.
- D — Slower than Team 2 with a stronger team.
At what time is the order complete?
Reveal answer + reasoning
- A — Assumes R is as fast as the broken P: 1,600 ÷ 1,000 = 96 minutes.
- C — Forgets R: Q alone needs 4 hours.
- D — Keeps P running after it broke: 1,600 ÷ 1,200 = 80 minutes.
Can you solve these time and work questions?
🙅 Myth
Two people together take the average of their times.
Tap to bust it →
🙅 Myth
Double the people, half the time. Always.
Tap to bust it →
🙅 Myth
Wages are split by speed.
Tap to bust it →
🙅 Myth
"Leaves after 3 days" = "leaves 3 days before the end".
Tap to bust it →
Q1. Working together, how long do they take?
LCM 12: rates 2 and 1, so 12 ÷ 3 = 4 hours. 9 averages the times; 18 adds them.Q2. How long would all three take together?
LCM 60: pair rates 5, 4 and 3. Their sum, 12, counts everyone twice, so all three do 6 a day: 10 days. 5 forgets to halve.Q3. How long would Rohan take alone?
Rates 3 : 1, so the job is 4 × 9 = 36 units; Rohan does 1 an hour. 12 is Aarav's time.Q4. How many more days will the clean-up take?
Job = 120 volunteer-days; 30 done, 90 left for 20 people: 4.5 days. 6 ignores the new five; 6.5 adds the first 2 days.Q5. How long would one helper take alone?
The two helpers together do 1/6 − 1/15 = 1/10 a day. Each takes 20 only if they are equally fast, which the passage never says.- Work piles up as rates: n days means 1/n of the job a day.
- LCM method: job = LCM of the times, so every rate is whole.
- Together time: between half the faster time and the faster time.
- Wages follow rate × days worked.
- Rate = 1/n a day; work = rate × time
- Two together: a × b ÷ (a + b)
- Together T, one alone a → other alone = a × T ÷ (a − T)
- Efficiency ratio = inverse of the time ratio
- M1D1H1 ÷ W1 = M2D2H2 ÷ W2 (identical workers)
- Pipes: fill +1/a, leak −1/b
Frequently asked questions
What is the LCM method in time and work?
What is the formula when two people work together?
Why can't you average the times in time and work?
How is time and work related to pipes and cisterns?
Keep going
Connected topics in other chapters
Every topic in Profit, Interest & Time-Speed-Work
- 1.Profit and Loss: CP, SP and Profit %
- 2.Marked Price and Discount: Mark-up, Sale Price and Profit
- 3.Successive Discounts and Discount Schemes: the Single Equivalent Discount
- 4.Cost, Revenue and Per-Unit Price in Caselets
- 5.Simple Interest: Formula, Shortcuts and CLAT Traps
- 6.Compound Interest and the SI–CI Difference
- 7.Speed, Distance and Time
- 8.Trains, Races and Relative Speed
- 9.Time and Work: the LCM Method (you're here)
- 10.Pipes and Cisterns