What counts as a breach of contract?
A breach is a failure to perform as promised without lawful excuse. That last part is the filter. If performance became impossible through no one's fault, the contract is frustrated, not breached, and nobody owes damages. Late, defective or half-done performance, or a flat refusal, all count.
- โขNot done, or done late or badly
- โขClaim arises on the due date
- โขRefusal before the due date
- โขOr disabling yourself in advance
| Test | Actual | Anticipatory |
|---|---|---|
| Example | Caterer doesn't show on the wedding day | Caterer emails a month early: โTook another bookingโ |
| When to sue? | From the due date | At once, or after waiting |
An advance refusal is a real breach. You needn't wait for the date.
-
1
Day 1Contract madeZoya hires Aarav to photograph her event on 1 March.
-
2
1 FebAarav repudiatesโFound a better gig. Not coming.โ
-
โ๏ธ
Option AAccept and end itZoya sues now and hires someone else, keeping her losses down.
-
โณ
Option BKeep it aliveThe contract binds both sides, and Aarav may still change his mind.
-
โ ๏ธ
RiskSomething intervenesIf a lockdown cancels the event first, frustration frees Aarav. By waiting, Zoya lost her claim.
What remedies does the injured party have?
Quantum meruit helps only the innocent party. If a publisher scraps a series halfway, the author is paid fairly for chapters written, though the fee was due on completion. A writer who walks out mid-way can't claim it.
Which losses can you actually recover?
Damages compensate; they don't punish. But one breach can set off a long chain of consequences, and the law cuts the chain at remoteness. Remoteness has two limbs.
- โขArises in the usual course of things
- โขNo special notice needed
- โขArises from unusual circumstances
- โขRecoverable only if known when contracting
| Test | Ordinary loss | Special loss |
|---|---|---|
| Steel not delivered | Extra price to buy elsewhere | A lucrative resale deal, only if the seller was told |
| Courier delays a part | The cost of the delay | Factory shutdown profits, only if disclosed |
Anything outside both limbs is remote. You can't recover it.
What cuts down the damages you get?
- โMitigation. Take reasonable steps to limit loss. A sacked employee who refuses an equal job next door can't claim a year's salary.
- โReasonable, not heroic. You needn't take big risks or spend wildly to mitigate.
- โMarket measure. For undelivered goods: market price on the delivery date minus contract price. If the market fell, you lost nothing in money.
- โNominal damages. A breach with no provable loss still earns a token sum.
- โNo punishment. A cynical breach costs the same as a careless one.
- โMental distress. Usually not paid, unless the contract's very purpose is enjoyment or peace of mind, like a holiday package or a long-delayed home.
| Fact twist | Effect |
|---|---|
| Special purpose disclosed after signing | Special loss not recoverable |
| Victim let perishable goods rot instead of reselling | Reduced: no mitigation |
| โCompensation for shockโ over a late sofa | Not recoverable |
What if the contract already names the amount?
โโน10,000 per day of delay.โ โDeposit forfeited if you back out.โ English law splits such clauses into a genuine pre-estimate (liquidated damages, enforced) and a threat (penalty, not enforced). Indian law doesn't bother. Whatever the label, the court awards reasonable compensation up to the named sum.
- 1
Find the ceilingAdd up everything the clause takes on breach: payments, forfeitures, extra interest.
- 2
Check for legal injuryExact proof of loss isn't needed, but a breach causing no loss at all earns nothing.
- 3
Fix a reasonable figureNever above the ceiling.
When will a court order performance instead of money?
Specific performance used to be the exception, granted only where money was inadequate (land, a rare painting). Indian law now makes it the rule, with set exceptions. If a passage states the old โdamages inadequateโ test, apply the passage.
- Personal skill: no court forces a singer to sing.
- Constant supervision: a ten-year maintenance deal is beyond policing.
- Substitute already obtained at the defaulter's cost.
- Terminable at will: pointless to order.
The injunction fills the gap. A court won't make a star perform at your venue, but if she also promised not to perform elsewhere that season, it can stop her performing for a rival.
Which cases built these rules?
How has CLAT asked it?
Choose the most reasonable conclusion.
Reveal answer + reasoning
- A โ X was paid and has no claim.
- B โ assumes a breach that never happened.
- C โ true, but the dispute is Y's claim; D answers it.
Choose the most reasonable conclusion.
Reveal answer + reasoning
- B โ real law, but it contradicts the stated principle.
- C โ C is a stranger to the AโB contract.
- D โ the principle says nothing about damages.
๐
Myth
You can't sue until the performance date.
Tap to bust it โ
๐
Myth
The defaulter pays for every loss caused.
Tap to bust it โ
๐
Myth
A โน5 lakh breach clause means โน5 lakh.
Tap to bust it โ
๐
Myth
After a breach, I can let losses pile up.
Tap to bust it โ
Q1. When can Meher sue?
Anticipatory breach: accept and sue at once.Q2. What will Rohan recover?
Mitigation: accepting would have avoided most of the loss.Q3. Is the stipend recoverable?
Special loss, disclosed at contracting, so it's within the second limb.Q4. What does the buyer get in India?
The named sum is a cap.Q5. What can a court give Kabir?
No forced personal service, but the negative promise is enforceable.- Breach: non-performance without lawful excuse, actual or anticipatory.
- Anticipatory breach: sue now, or keep the contract alive at your own risk.
- Damages: natural losses, plus special ones both sides knew at contracting.
- Mitigate; no punishment, and rarely mental-distress money.
- Named sums are a ceiling. Specific performance and injunctions enforce the deal itself.
- Indian Contract Act, 1872: s.39 refusal to perform (promisee may end the contract); s.73 damages, remoteness and mitigation (Explanation); s.74 penalty and named sums; s.75 compensation on rightful rescission.
- Specific Relief Act, 1963 (amended 2018): s.10 specific performance as the rule; s.14 exceptions; s.20 substituted performance; s.42 injunction on negative agreements.
- Cases: Hadley v Baxendale (1854); Hochster v De la Tour (1853); Avery v Bowden (waiting lost the claim when war broke out); Fateh Chand, AIR 1963 SC 1405; Ghaziabad Development Authority v UoI, AIR 2000 SC 2003 (mental distress).
Frequently asked questions
What is the difference between actual and anticipatory breach?
Can I claim damages for mental agony caused by a breach?
Are liquidated damages and penalty the same in India?
Can the party who broke the contract claim quantum meruit?
Is specific performance still discretionary?
Keep going
Connected topics in other chapters
Every topic in Law of Contracts
- 1.Offer and Acceptance for CLAT: How a Deal Is Born
- 2.Invitation to Offer vs Offer: The Shop-Window Trap
- 3.Postal Rule, Revocation and Online Acceptance
- 4.Consideration: Something for Something
- 5.Privity of Contract: Who Can Sue?
- 6.Family Promises vs Business Deals: Intention to Create Legal Relations
- 7.Minor's Agreement for CLAT: Why It's Void (Not Voidable)
- 8.Coercion vs Undue Influence: The Pressure Tests
- 9.Fraud vs Misrepresentation: Lies, Half-Truths and Silence
- 10.Mistake of Fact vs Mistake of Law in Contracts
- 11.Void vs Voidable vs Illegal: Getting the Label Right
- 12.Lawful Object and Public Policy: When the Purpose Kills the Deal
- 13.Restraint of Trade: Non-Compete Clauses Explained
- 14.Wagering Agreements: Bets, Lotteries and Insurance
- 15.Contingent Contracts: "If This Happens, Thenโฆ"
- 16.Frustration and Discharge: When a Contract Dies
- 17.Breach of Contract and Damages: What Can You Claim? (you're here)
- 18.Quasi-Contracts: Obligations Without an Agreement
- 19.Indemnity vs Guarantee: Who Pays If It Goes Wrong?
- 20.Agency in Contract Law: Acting for Someone Else